Daily Work Log


Deprecated: preg_replace(): The /e modifier is deprecated, use preg_replace_callback instead in /home/nachbar/xltaweb.com/buildlog/wp-includes/functions-formatting.php on line 76
Date Hours Who What
         
Sun Jan 8 3 Kevin Shop setup
Sun Jan 8 3 Dan Shop setup
Sun Jan 8 3 Kevin Cutting panels 3 and 4
Sun Jan 8 3 Dan Cutting panels 3 and 4
Mon Jan 9 0   Lost in sewing machine hell.
Tue Jan 10 8 Kevin Sewing panels 3 & 4
Tue Jan 10 1 Kevin Cutting panel 5
Tue Jan 10 1 Dan Cutting panel 5
Wed Jan 11 1 Kevin Cutting panel 2
Wed Jan 11 1 Dan Cutting panel 2
Wed Jan 11 10 Kevin Sewing panels into gores
Thu Jan 12 5 Kevin Cutting panels 6,7,8, & 9
Thu Jan 12 4 Dan Cutting panels 6,7,8, & 9
Thu Jan 12 10 Kevin Sewing panels into gores.
Fri Jan 13 5 Kevin Cutting panels 10,11,12, & some of 13
Fri Jan 13 4 Dan Cutting panels 10,11,12, & some of 13
Fri Jan 13 1.5 Kevin More sewing panels into gores.
Sat Jan 14 9 Kevin Yet more sewing panels into gores.
Sun Jan 15 7 Kevin Yet still more sewing panels into gores.
Mon Jan 16 7 Kevin Even yet more sewing panels into gores.
Tue Jan 17 0 Kevin Waiting for the last of the materials.
Wed Jan 18 0.5 Dan Cutting last piece of panel #11.
Wed Jan 18 0.5 Dan Put away cutting table and rearrange shop.
Wed Jan 18 0.5 Kevin Put away cutting table and rearrange shop.
Wed Jan 18 0.5 Kevin Cutting last piece of panel #11.
Wed Jan 18 1 Kevin Cutting panel #13.
Wed Jan 18 3.5 Kevin Sewing last of the nylon onto gores.
Wed Jan 18 3.5 Kevin Attached first 3 vertical load tapes.
Wed Jan 18 3 Kevin First vertical seam
Thu Jan 19 9.5 Kevin More vertical seams and load tapes.
Fri Jan 20 11 Kevin Yet more vertical seams and load tapes.
Sat Jan 21 8.5 Kevin Finished vertical seams and load tapes.
Sun Jan 22 10 Kevin Attached all 3 horizontal tapes.
Mon Jan 23 5 Kevin Misc bits and cutting pieces for parachute.
Tue Jan 24 2 Kevin Sewing section of parachute together.
Tue Jan 24 1.5 Kevin Scribing circle for parachute.
Tue Jan 24 2 Kevin Hemming and finishing parachute.
Tue Jan 24 1 Dan Scribing circle for parachute.
Wed Jan 25 7.5 Kevin Misc bits on top including vent attachment points.
Thu Jan 26 8 Kevin More finish work on top and vent.
Fri Jan 27 13 Kevin Cut and attached Nomex panels at bottom of gores.
Sat Jan 28 12 Kevin Finished vertical seams at bottom and
terminated load tapes at the bottom.
Sun Jan 29 20 Kevin Closed envelope
finished tops of load tapes
Attached top ring
Wed Feb 1 4 Kevin Corrected a flaw in seam
Reworked a parachute attachment point
Constructed carrying bag

Total for Kevin: 187 hours

Total for Dan: 18 hours